Pan Borneo Highway Nyabau – Bakun junction construction progress

Nyabau – Bakun junction section of the Pan Borneo highway works started on March 2015 covering a distance about 43km long.

The project main contractor is Pekerjaan Piasau Konkerit Sdn. Bhd.

There are four bridges, 26 bus shelters and two pedestrian bridges along this stretch of Pan Borneo highway.

Pan-Borneo highway recently made an update on the work progress along the highway which is expected to be fully completed by year 2023.

Here are some of the latest photos from the project courtesy of Pan Borneo Highway.

Piling and cultvert work. (Pix. Pan Borneo Highway)

This is aerial view of bridge no.4 over Simalajau River. (Pix. Pan Borneo Highway)

Work progress on bridge no.3 Sibiew River 3. (Pix. Pan Borneo Highway)

Embankment and filling works. (Pix. Pan Borneo Highway)

Laying concrete on roadside drain.

Completed cross beam bridge pier 1 over Sibiew River 1, near Nyabau. (Pix. Pan Borneo Highway)